UNILEVER - Project Waterfall - Phase ONE the "Processing Plant"

Installation of a chemical processing plant
Unilever and Project Waterfall, Johannesburg, South Africa

Another great longterm timelapse project is complete! This time it was for Project Waterfall from Unilever while they were installing a chemical processing plant inside a warehouse. We had two static cameras installed to capture the progress of this new chemical plant.

The installation process started in early September 2014 and took less than 2 months to complete.

Here are some interesting statistics from the project:

  • Valves - 2309
  • Bolts & Nuts - 31660
  • Steel - 335 tons
  • Piping - 5636 meters
  • Big Modules - 19
  • Fabrication - 2 months
  • Workers - 70 Workshop Personnel
  • Designers - 28 Design Engineers
  • Duration - ± 45 Days

CREDITS:

Executive Producer: Unilever
Produced by: TimeLapse SA
Directed by: Joe Louw / Jonelle Louw
DP: Joe Louw
Offline editing & grading: Jonelle Louw
Online editing & Graphics: Nanette Grebe - Handmade Media